TYLER – Here’s a look at work planned in the district during the Weeks of June 27th. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.
Smith County construction projects updates:
Loop 323 West Widening
*Limits: Tyler’s West Loop and SH 31
*Contractor: Longview Bridge and Road, Ltd., of Longview
*Cost: $12 million
*Anticipated Completion Date: Winter 2016
The contractor continues to excavate the existing northbound lanes as well as conduct work on the new railroad bridge and Bellwood Road West. A temporary detour is in place. The project includes widening Loop 323 from SH 31 to Shaw Street. The speed limit on Loop 323 in the work zone has been reduced to 45 mph from SH 64 to
Shaw Street. Continue reading TxDOT Road Projects