Posted/updated on: December 21, 2010 at 2:24 am


TYLER — Here is the monthly construction update for projects in the Tyler district of the Texas Department of Transportation.

The Texas Department of Transportation’s Tyler District has announced it expects to complete three projects before the end of the year, bringing the total number of projects under construction to 15 across the Tyler District. “Things are obviously slowing down for the holidays and the cooler weather,” said TxDOT spokesman Larry Krantz. “But 2011 is going to be a busy year.” TxDOT contractor Garey Constriction, Ltd., of Austin, completed the final U.S. Highway 175 expansion project in Henderson County in December, closing the book on a $26 million project that added two lanes to the highway between Eustace and the Kaufman County Line. The project began in earnest in December 2007.

Contractor R.K. Hall, of Paris, Texas, also completed a pair of small projects in Wood County, which called for adding shoulders to Farm Road 779 between Farm Road 17 and Farm Road 1799 in Golden, and to Farm Road 69 between Farm Road 515 in Coke and State Highway 37 in Quitman. The combined $3.5 million projects broke ground late this past spring.

In January, contractor A.L. Helmcamp, of Buffalo, Texas, is set to begin a project to add shoulders to Farm Road 344 between Farm Road 346 in Teaselville and U.S. Highway 69 in Bullard. “This project is among the first of several safety-related projects we’re going to be working on this summer,” Krantz said. “A majority of those projects a designed to add three-foot shoulders to narrow Farm-to-Market roads in the hopes that the extra six feet of pavement may be the difference between a wreck and a near-miss.” The $2.2 million project let to contract in August and is scheduled to take approximately six months to complete.

TxDOT also let three projects to contract in December, including a pair of projects calling for shoulder-widening similar to the Farm Road 344 project. In Cherokee County, contractor Big Creek Construction won the bid to add shoulders to and resurface Farm Road 752 south of Rusk, and Farm Road 2137 between Farm Road 344 near Bullard and Farm Road 855 north of Cuney. The approximate $978,000 project is scheduled to begin in the spring.

In Henderson County, contractor A.L. Helmcamp won the bid to add shoulder to and resurface Farm Road 314 between the Van Zandt County Line and State Highway 31 in Brownsboro. The approximate $687,000 project is scheduled to begin in the spring.

Also in Henderson County, Big Creek Construction won the bid to repair and resurface State Highway 31 between Brownsboro and the east end of Farm Road 3204. The approximate $3.9 million project is scheduled to begin in the spring. TxDOT also has plans to let one project to contract in January.

In Henderson County, TxDOT is planning an estimated $1.4 million project to repair and resurface Ranch Road 2329 between Farm Road 316 and U.S. Highway 175. The project would likely begin in the late spring or early summer.

TxDOT-Tyler District at-a-glance
Projects marked for completion in December:

*U.S. Highway 175-Adding two additional travel lanes to US 175 between Eustace and the Kaufman County Line. The $25.8 million project is on schedule to be completed by the end of 2010. Garey Construction, Ltd. of Austin, Texas, is the contractor.
*Adding shoulders to Farm Road 779 between Farm Road 17 and Farm Road 1799 in Golden. The approximate $1.5 million project let to contract in March and is scheduled for completion in December. R.K. Hall Construction of Paris, Texas, is the contractor.
*Adding shoulders to Farm Road 69 between Farm Road 515 in Coke and State Highway 37 in Quitman. The approximate $2 million let to contract in March and is scheduled for completion in December. R.K. Hall Construction of Paris, Texas, is the contractor.

Projects set to begin in January:
*Resurfacing and adding shoulders to Farm Road 344 between U.S. Highway 69 in Bullard and Farm Road 346 in Teaselville. The estimated $2.2 million project let in August. A.L. Helmcamp, Inc. of Buffalo, Texas, is the contractor.

Projects let to contract in December:
*Adding 3-foot shoulders and resurfacing Farm Road 752 between Farm Road 241 in Rusk to CCR 2405 south of Rusk; and Farm Road 2137 between Farm Road 344 west of Bullard and Farm Road 855. The approximate $978,000 let in December and is scheduled to begin in the spring. Big Creek Construction, Ltd., of Hewitt, Texas, is the contractor.
*Adding 3-foot shoulders and seal-coating between the Van Zandt County Line and HCR 3300, approximately one mile north of State Highway 31 in Brownsboro. The approximate $687,000 project let to contract in December, is scheduled to begin in the spring and take approximately four months to complete. A.L. Helmcamp, Inc., of Buffalo, Texas is the contractor.
*Repair and resurface between Farm Road 314 in Brownsboro and the east end of Farm Road 3204. The approximate $3.9 million project let in December and work is scheduled to begin in the spring. Big Creek Construction, Ltd., of Hewitt, Texas, is the contractor.

Projects scheduled to let to contract in January:
Repair and resurface between Farm Road 316 and U.S. Highway 175. The estimated $1.4 million project is scheduled to let in January and begin in the late spring or early



News Partner